Kitimat infrastructure repair costs climb by $550,000


Kitimat infrastructure repair costs climb by $550,000

Published 9:30 am Wednesday, October 28, 2026

Getting your Trinity Audio player ready…

Two infrastructure repair projects will cost an additional $550,000 after construction bids exceeded their budgets, but the District of Kitimat will cover the increase by redirecting money from other projects rather than seeking new funding.

The Creed Street stormwater repair project accounts for most of the increase, with its budget rising by $425,000 to $1.125 million. The courthouse roof replacement will cost another $125,000, bringing its total budget to $375,000. Together, the projects are now expected to cost $1.5 million, compared with the original combined budget of $950,000.

The additional spending raised concerns from Coun. Gerry Leibel at the Oct. 5 council meeting about the continued movement of money between infrastructure projects rather than maintaining dedicated reserves for future work.

“We’re always robbing Peter to pay Paul, and I think we should have a better balancing act,” Leibel said.

Although he supported the repairs as necessary infrastructure investments, Leibel suggested council commit to setting aside money annually in dedicated infrastructure reserves to reduce the need to transfer funding from one project to another.

The additional $550,000 will come from two existing project budgets, with $250,000 redirected from the annual walkway reconstruction program and $300,000 from the Eco-Depot design project.

Email newsletter signup

The walkway work is expected to cost $350,000 against its $600,000 budget, freeing up the remaining $250,000. The project involves replacing walkways in the Nechako neighbourhood near Oriole Street to address tripping and ice hazards near Nechako Elementary School. District crews are completing the work at a lower cost than originally budgeted.

The Eco-Depot funding is being released following LNG Canada’s commitment of $5 million toward construction of the facility.

The largest cost increase involves the replacement of approximately 100 metres of storm sewer along Creed Street, where a failure in 2025 caused drainage problems and created risks to nearby properties and Sumgas Creek.

The damaged sewer has caused stormwater to back up and discharge in an area not designed for drainage, increasing the risk of damage to adjacent properties and trees, as well as sediment entering the creek.

The original project budget did not account for emergency work undertaken earlier this year, including pump rentals and construction of an interim drainage ditch. The replacement is also complicated by the sewer’s depth of approximately six metres and the need to work around sensitive slopes, according to a staff report.

The courthouse roof replacement has also become more expensive because of the limited number of local contractors certified to install institutional roofing. Both the flat and sloped roof sections have exceeded their service life, and recurring leaks are disrupting tenant operations.

Coun. Terry Marleau supported the importance of maintaining infrastructure but questioned whether rising construction prices could eventually force the District to consider contractors from outside the community.

“Are we going to get to a point down the line where the cost gets prohibitive, are we looking at other options down the road?” he asked.

Marleau emphasized his support for local contractors but wanted to know whether the District would be prepared to consider alternatives if costs continued to climb.

Director of engineering Alex Ramos-Espinoza said construction tender results have varied throughout the year. Four projects tendered earlier in the year came in below budget, while the three most recent tenders have all exceeded their allocations.

“We have looked at options on how we can make it more competitive and one item we’ve considered is combining projects to get more interest. That being said, that requires higher budgets than council is considering,” Ramos-Espinoza said.

Ramos-Espinoza added that the tenders for the current work include a five per cent contingency, although unforeseen complications could still push costs higher. He described that possibility as slim.

The staff report warned that delaying the Creed Street repairs could cause further damage to neighbouring properties and potential environmental harm. Leaving the courthouse roof unrepaired would mean continued leaks, higher maintenance costs and further disruption for tenants.

Council unanimously approved the $550,000 budget reallocation, allowing both projects to proceed using existing approved funding without increasing the operating budget.

You Might Like

News
HIGHLIGHTS: Red Deer Rebels outgun Saskatoon Blades in high-scoring affair

News
Red Deer council supports move to multi-year budgets beginning in 2028

News
Rick Hansen guest of honour at exclusive documentary screening in Williams Lake

News
Victoria tops the nation in DIY Halloween costume searches; Kelowna 3rd, Vancouver 5th

Leave a Reply

Your email address will not be published. Required fields are marked *