Contractor confirms Revelstoke’s Highway 1 rest area reopening end of month
|
Getting your Trinity Audio player ready…
|
Eight months’ work to upgrade Revelstoke’s Trans-Canada Highway rest stop is slated to finish by end of month, the province’s contractor says.
The Ministry of Transportation and Transit awarded Okanagan Aggregates Ltd. a $12-million contract last year to expand, repave and improve the safety, accessibility and amenity of the Columbia rest area.
The site has been closed off for construction since April 1, but general manager Randy Zbytnuik said the project is on track to finish and reopen this important rest area in a week-and-a-half.
READ: Minister says accessibility is key as renovations begin at Revelstoke rest stop
He told Revelstoke Review on Friday, Nov. 20, that Okanagan Aggregates has finished paving and line-painting work that began earlier this month.
Crews are still assembling eight new flushing washrooms with wheelchair ramps, and seven electric vehicle charging stations have been added.
“Much more capacity,” Zbytnuik said. “Just making that much more user-friendly.”
He estimated that the upgraded rest area now has about 30 per cent more capacity — “it’s quite a bit bigger” — along with clear flow-of-traffic lines.
The big difference from before will be that all traffic must now enter and exit the rest area via Westside Road. Westbound access off Highway 1 will no longer be possible.
Allowing vehicles back into the site this December will fill a 100-kilometre gap along Highway 1 that’s existed most of this year for commercial traffic needing somewhere to break or wait out closures — and just in time for the snow.
“It’s a pretty vital rest area,” Zbytnuik noted, referring to regular delays between the Shuswap and Rogers Pass in winter for highway maintenance and avalanche control. “It’s important, especially during all the closures.”
READ: ‘Check DriveBC’: Revelstoke highway contractor preps for winter maintenance, traffic and weather
After reopening the rest area within two weeks, Okanagan Aggregates will return in spring 2027 to finalize some landscaping and cleanup work around the rest area.
It recently also wrapped up work installing islands and improved lighting near the Highway 23 North intersection, and supplied Green Roads Recycling with asphalt to repave Highway 1 around the bridge.
Zbytnuik said his crews are seasoned in rest area construction and recently completed road and intersection improvements to Highway 1 near Field and the Alberta border as well.
Until upgrades at the Columbia rest area conclude, commercial vehicles should continue stopping at either the Illecillewaet brake check to the east or the Last Spike area to the west. The Rutherford Beach area west of Revelstoke and Shelter Bay south of town are also open to passenger vehicles exclusively.
For the latest updates on Revelstoke’s rest stop, check drivebc.ca.
You Might Like
News
Doerkson lays out immediate priorities, explains B.C. cabinet picks
News
Whitecaps Player Awards for 6 ahead of playoff-opener Sunday at BC Place
News
RCMP seek truck that allegedly drove over tent, injuring Vernon occupant
News
Okanagan Legion branch put under trusteeship